Framework Agnostic Capacity Planning at Scale - Nick Brown | Craft 2025

June 04, 2026

Framework Agnostic Capacity Planning at Scale - Nick Brown (Talk Outline)

A Craft 2025 conference talk by Nick Brown — a seasoned agility and product consultant, currently principal flow consultant at Thrive Partners, who has led agility adoption at PwC, Nationwide, Royal Mail, and ASOS, builds open-source tools for Jira and Azure DevOps teams, and (per his intro) once owned a racehorse that broke even. He admits the “fancy name” was chosen so people would attend a talk that is really about making planning easier. Format: a single-speaker slide talk (with recurring “how does it work in the real world?” payoff moments and real anonymized team data) followed by an extended Slido Q&A. The talk’s own structure: critique the standard definitions and tools → name the problems → ground it in a real quarterly-planning failure → introduce the inspirations and the “framework-agnostic” idea → teach three practices (right-size features, forecast to confidence levels, continuously reforecast) → show it scaling from teams to platforms to domains → getting-started advice → Q&A.


1. What “Capacity Planning” Should Mean

1.1 The talk’s real intent

  • The fancy title exists so people would show up; the real subject is planning in a more effective manner.
  • Capacity planning is something everyone working with agile teams has “invariably experienced.”
  • Nick’s habit for talks: Google the topic and react to the top results.

1.2 Definition #1 — the circular non-definition

  • First search result: “agile capacity planning is a part of the agile planning process in which you calculate the capacity of your team.”
  • His reaction: it’s circular — “doesn’t really tell us anything.”

1.3 Definition #2 — the scrum-centric, project-manager version

  • “Capacity planning is the process of evaluating the amount of productive time available in each sprint. Project managers use capacity planning to schedule work and manage software delivery.”
  • Two problems: it’s very focused on Scrum, and it invokes a project manager — a role that isn’t part of Scrum.
  • His read: “that looks like a project manager wrote it.”

1.4 Definition #3 — the one he likes (evidence-based)

  • Capacity planning creates evidence-based expectations of what your team can achieve.
  • Session goal: leave with tools, techniques, and real-world examples used in his organization to manage capacity expectations using data and evidence.

2. The Bad Tools and Templates in the Wild

2.1 The Smartsheet Gantt template

  • Columns: resource, name, status (unclear — of the person? of the work?), start/end date, duration.
  • Plotted as a Gantt visual.
  • Quoting Carl Scotland: “that’s not my agile” — not the agile he recognizes.

2.2 The Agile Digest Excel template (“$70, down from $75”)

  • “Hot off the press,” discounted to $70 from $75; the big team capacity planning template supports up to 40 members.
  • It’s an Excel file with a 15-minute video just to explain it — “it takes 15 minutes to explain the Excel file.”
  • Rows telling you when someone does or doesn’t have capacity. “Again, that’s not really my agile.”

2.3 The Scrum Alliance case study (one of the better ones)

  • A case study with multiple agile teams on the same product/initiative.
  • Good definition: how much valuable work in a unified backlog can reasonably be accomplished by multiple teams.
  • Uses SWAG estimates to see who has capacity and where a team (e.g., a backend team) has a problem.

2.4 SAFe and “normalized story points” (probably the worst)

  • Normalizing story points across teams: everyone gives something a “1” and that becomes the shared reference.
  • The negative part: it mandates a single way of working — everyone must estimate in story points, and a story point is supposed to mean the same everywhere.
  • “Invariably it doesn’t” mean the same.

3. The Problems With These Approaches

3.1 Playing Tetris (cramming instead of limiting WIP)

  • They focus on cramming in as much as possible — like fitting lines in Tetris.
  • The opposite of what’s wanted: limiting the amount of work in progress and encouraging focus before moving on.

3.2 The “frozen middle manager” squeezed from both sides

  • The middle manager is “held at gunpoint” by both sides.
  • Senior leaders say: “get in control.”
  • Teams say: “empower us — we want to choose how we work, how we estimate, how we plan.”
  • Result: managers default to the not-so-good techniques because they want to be seen as in control.

3.3 It takes far too long

  • Capacity planning sessions in “war rooms” take hours, if not days.
  • With the right information, data, and method it should take seconds, at most minutes.

4. Why This Is Relevant — A Real Quarterly-Planning Failure

4.1 The setup

  • An image from a quarterly planning session at an organization Nick used to work in.
  • Every quarter, people across the technology org gathered with a prioritized, stack-ranked list of initiatives (each given a prioritization score).
  • Outcome ratings: good to go, amber (might not make it), red (“you ain’t got a chance — we’re not doing this”).

4.2 Problem — a misaligned understanding of “capacity”

  • Most people take “capacity” to mean capacity to do/finish something (per sprint, extrapolated to the quarter).
  • Some teams read it as “capacity to start — “a very weird definition.”
  • Illustrated with the Jeff Patton image about alignment vs. differing understandings.

4.3 Problem — pure guesswork

  • Teams asked about capacity largely guessed: “I don’t know, I think we might make it.”
  • Finger-in-the-air guesswork, not using evidence they already had.

4.4 Problem — fake “data-driven” (velocity plus buffer)

  • Other teams thought they were data-driven: planning a number of points per sprint plus a buffer / catch-up for later sprints.
  • Masqueraded as scientific / data-driven — “which it most definitely was not.”

5. Inspirations and the “Framework-Agnostic” Idea

5.1 Prateek Singh — probabilistic thinking

  • Highly recommends his book and talk.
  • A conference talk four years ago: ”how many bottles of whiskey will he drink in four months” — it’s about agility, “not the confessions of an alcoholic.”
  • Lets you apply capacity-planning ideas in a non-software context.

5.2 The book Scaling Simplified

  • One of his favorite books of the last 10 years.
  • About scaling agility practices without being regimented (“do we do Scrum, Kanban, SAFe, LeSS?”).
  • Focus on scaling flow practices and how they enable better delivery at all org levels.

5.3 What “framework-agnostic capacity planning” means

  • A common approach to capacity planning across multiple teams that still allows each team autonomy in its way of working.
  • In this org: roughly 100 teams — some use Scrum, some Kanban, some a blend, some continuous flow.
  • They encouraged this diversity because that’s where the best software/product teams come to life — with autonomy over their way of working.

5.4 The three practices (overview)

  • Practice 1: Break features down consistently (right-sizing).
  • Practice 2: Forecast to confidence levels.
  • Practice 3: Continuously reforecast.

6. Practice 1 — Break Features Down Consistently (Right-Sizing)

6.1 What “feature” means here

  • “Feature” = the level above story — call it epic, initiative, whatever; “I don’t really care.”
  • In this org they called it features.
  • Goal: focus on getting features to done the same way you focus on getting stories to done.

6.2 Slicing techniques to enable it

  • Requires slicing features into small, thin vertical slices.
  • Neil Kick — capability slicing, functional slicing, implementation slicing (different ways to slice a higher level).
  • Jeff Patton’s story mapping — plot the user’s journey/flows, then identify the first deliverable slice that yields feedback and potential value.

6.3 The right-sizing concept (the fish tank)

  • Right-sizing = making features no bigger than a certain size.
  • Accept variation — not every feature is the same — but keep them under a ceiling.
  • Metaphor: a fish tank fitting multiple sizes of fish (though the big one on the left “might be a struggle”).

6.4 The scatter plot with percentile lines

  • For each team, visualize features completed in a time horizon (for simplicity, the last 12 weeks).
  • Each dot = one completed feature/epic, plotted by completion date (x) vs. number of child items (y).
  • Draw percentile lines showing what percentage of features had a given child-item count.
  • Real example: 85% of completed features had 7 child items or fewer → the right size = 7 child items.
  • So aim: keep features 7 or fewer (some 1, 3, 5, 7 — the vast majority ≤7).

6.5 Visualizing open features against the right size

  • Also visualize open features (started or not yet started) and their child-item counts, ordered by count.
  • Below right size → fine (but the tool only knows what’s entered; add items when appropriate).
  • At right size → a warning: be careful about adding more.
  • Above right size → a red flag; the top one shown was more than double the right size.

6.6 Teams control the percentile

  • Default was the 85th percentile.
  • Teams could choose 95th, 70th, 50th — entirely their control.
  • Not “every team must use 85th or else.”

6.7 Real-world team example — 26 → 10 child items

  • A team liked the approach and looked at their own data.
  • Period 21 Aug – 21 Oct 2023: 4 completed features, right size of 26 child items or fewer, average cycle time 40 days (he apologizes to “Dan” for using the average).
  • They decided their features were too big and changed the right size to 10 child items or fewer.

6.8 The result after the change

  • In the following two months: 19 features completed.
  • Batch size now 5 child items or fewer (vs. 26).
  • Average cycle time dropped from 40 days to 23 days.
  • Simply: more, in smaller batches, quicker than before — “the essence of agility,” enabling faster feedback on whether it’s the right thing.

6.9 Gaming — the bad and the good kind

  • Bad gaming: faking slices — a “backend feature,” a “front-end feature,” even a “deployment feature” (“if you’re feeling really creative”) that aren’t slices of value.
  • Good gaming: if breaking down still yields thin vertical slices you can get feedback on — that’s encouraged.

6.10 Prerequisite — actually move features/epics to done

  • Teams must genuinely get features to done, not just stories.

6.11 Prerequisite — the work-item-age chart

  • A complementary tool: work item age chart showing days a feature/epic has been in progress vs. its status/column.
  • Includes percentiles for feature cycle time.
  • Hovering a column reveals all items in it and how many child items remain or are completed.

6.12 Prerequisite — regularly monitor feature size

  • Ask questions like: this feature has 73 child items but the right size is 16 — is it really an MVP?
  • “Probably not — probably the bastardized definition.” Break it down for faster feedback.

6.13 Prerequisite — slice at all levels

  • Break work into thin vertical slices at all levels, across all layers of the tech stack — not just one level.

6.14 Prerequisite — one team owns a feature

  • Avoid features shared by multiple teams; each team should own its part.
  • May require adding a level above (they chose “epic,” even if unsure it’s the right term).
  • The exact naming (capability > epic, epic > features, OKRs > features) doesn’t matter — it’s about an aggregating backlog level.

7. Practice 2 — Forecast to Confidence Levels

7.1 Deterministic vs. probabilistic thinking

  • Deterministic (how most were taught): assume one outcome — “this is the date we’ll be done.”
  • Typically: sum story points ÷ average velocity, or sum child items ÷ average completion rate.
  • Probabilistic: a range of outcomes, multiple possible ship dates, each with a probability.

7.2 The two approaches side by side

  • Deterministic: average throughput × weeks in a quarter → e.g., “this team has capacity for 36 items.”
  • Probabilistic: weekly completed range 1–5 items × 12 weeks = 12 to 60 things in the period.

7.3 Why the raw range isn’t practical

  • You can’t tell stakeholders ”12 to 60 items” — “you’re absolutely right,” not pragmatic.

7.4 Monte Carlo simulation (how to do it practically)

  • Instead of one burn-up producing one outcome, run it many times, each time sampling different historical data.
  • This yields a probability distribution across possible outcomes.
  • In this scenario, about 4,000 simulations → probabilities attributed to outcomes.
  • Read more under Monte Carlo simulation / probabilistic forecasting.

7.5 The forecast output

  • Using Jira / Azure DevOps data, for the next 12 weeks:
    • 95% likely70 items or more.
    • 85% likely76 items or more.
    • 50% likely86 items or more.

7.6 Combining forecast with right size → feature capacity

  • Combine the item forecast with the right size to get feature capacity.
  • At the 85th percentile: 76 items, right size ~4 child items/feature~19 features forecast for the next 12 weeks.
  • Few clicks → quick understanding of a team’s upcoming-quarter capacity.

7.7 Percentile is a team-controlled risk lever

  • Teams can pick 95th, 70th, even the 5th (“if they were feeling rather stupid”).
  • Based on their context, it lets them manage risk — “we’re not just saying that’s the number.”

7.8 Real-world validation — the quick sanity check

  • Quickest validity check: compare the forecast number (right) against the number of dots (left) — this period forecast vs. last period actual.
  • Three teams all chose the 70th percentile and the forecast was bang on vs. what they actually completed.

7.9 Real-world counterexample — bad data

  • One team completed 5 features but the model forecast 11 at the 85th percentile — more than double.
  • “Data doesn’t always equal the answer” — some teams had crap data.

7.10 “Computer says no” — data informs, doesn’t drive

  • Little Britain sketch: the woman in the wig behind the desk just taps keys and repeats ”computer says no,” with no pragmatism about the customer’s needs.
  • Lesson: data should inform decision-making, not drive it.

8. Practice 3 — Continuously Reforecast

8.1 Feature WIP = 1 (easy)

  • With only one feature in progress, forecasting is trivial.
  • Example: 10 child items remain; throughput of 4 → 6 left; next week complete 5 → 1 left.

8.2 Feature WIP = 2 (unpredictable splits)

  • With two features, the completion split is unpredictable: 0/4, 1/3, 2/2, 3/1, or 4/0 across features A and B.
  • Accounting for this over a quarter “becomes a bit of a pain.”

8.3 Apply probabilistic forecasting at the feature level

  • Use the same story-level probabilistic technique at the feature level.
  • Inputs: time horizon, confidence level, and — crucially — how many features run in parallel.
  • Note: “I don’t think I’ve ever come across a team that works on one feature at once.”

8.4 The feature forecast view

  • Left: open features from the backlog in the tool’s priority order (which may prompt teams to rethink priorities).
  • For each, look at child items remaining, then forecast how many weeks it will take from historical completion rates and other factors.

8.5 The color coding

  • Green — finishes before or on the target date.
  • Orange — misses by up to a week.
  • Red — misses by more than one week.
  • Teams can play with the parameters — “giving teams control,” showing “the consequence of your actions.”

8.6 Making “stop starting, start finishing” concrete

  • A common agile-coach slogan / laptop sticker: ”stop starting, start finishing.”
  • This tooling makes it real for people outside the “agile bubble”: fewer features in parallel → more gets done; more features → less gets done.

9. Does It Scale? — Real-World Application

9.1 The Miro board team section

  • A large Miro (digital whiteboarding) board; each team in a common area fills a section ahead of quarterly planning.
  • Data anonymized to protect individuals/teams.

9.2 Capacity minus carryover (the thing planning usually misses)

  • A team uses capacity planning to see how many features they have capacity for, plus Monte Carlo to see what won’t finish before the next planning event and will carry over.
  • Key insight: features/epics don’t magically finish at the planning boundary — they carry over.
  • Example team: capacity for 8 features, but 4 carry over → capacity for only 4 new features.

9.3 The 95th-percentile team (new members)

  • This team chose the 95th percentile because they have new team members, expecting reduced initial throughput during onboarding.
  • Went with 95% likelihood to manage expectations.

9.4 The 85th-percentile team (bigger features)

  • A different team chose the 85th percentile, capacity for 4 features, with bigger feature sizes and 2 items carrying over.

9.5 Rolling up — teams → platforms → domains

  • Teams grouped into platforms; platforms grouped into domains.
  • At platform level: what capacity do the teams have, what’s carrying over, and a link to their part of the Miro board.

9.6 The delivery plan (not a road map)

  • On the left, a delivery plan rather than a road map: when carried-over work is likely to finish (from Monte Carlo dates) and where the gaps are (e.g., some teams free around November–December).
  • Green dots = cross-team dependencies intact; red = dependencies broken.

9.7 The domain level and portfolio alignment

  • At domain level, multiple platforms aggregate; e.g., 26 of 40 features across teams already taken → some but not much spare capacity.
  • Portfolio alignment metric: each epic/feature correlates to a strategic pillar, and each pillar has a monetary value (cost saving or revenue) — “how accurate those numbers were, you can probably guess.”
  • Purpose: let teams, platforms, and domains see how much of their work aligns to strategy — “how much of our work goes all the way to the top” — because there’s nothing worse than working a story without knowing how it fits the big picture.

10. Getting Started — Advice

10.1 Make sure it’s a real problem worth solving

  • Don’t take it back to your org just because “it looks cool” — only apply it if it addresses a real problem.

10.2 Be prepared to explain it “again and again”

  • Expect to invest time explaining it repeatedly.

10.3 Use fictional data when real data is missing

  • If teams lack data to start, use fictional data to help them learn.

10.4 Sell it via benefits to the planning participants

  • Talk about it from the benefits to the people involved in planning — not as a consultant/coach lecturing about agility.
  • He and a colleague even adopted personas, Nick sporting a green wig as ”Nichollet Broom” (vs. Nick Brown).

10.5 Free GitHub templates

  • Free tools via a couple of GitHub repos: one for the capacity planning, one for flow metrics at the epic/feature level.
  • Download, connect to your org data, give it a go; expect bugs — raise them and he’ll try to fix them.

11. Summary

11.1 The closing points

  • In large organizations, capacity planning is a necessary technique.
  • It should be framework-agnostic — not prescribing that every team estimate in story points.
  • Use data — most of it likely already exists; you don’t need to radically overhaul teams.
  • Trust teams in the decision-making — don’t rely on data alone or become the “computer says no” persona; let data inform the team’s decision.
  • The three practices: break features down, forecast to confidence levels, continuously reforecast.

11.2 Personal plug

  • A book exists on doing (not just theorizing about) these things — with a 50% off code for conference attendees.
  • Invitation to connect on LinkedIn (“passively aggressively liking things that wind people up”).

12. Q&A (Slido)

12.1 Q1 — Fresh team, no historical data, short project — how to forecast predictability?

  • If someone on the team has experience, ask them.
  • Otherwise, guess and quickly reforecast as data arrives.
  • “Don’t overthink it.”

12.2 Q2 — How much trial/tinkering does a new team need for accurate estimations?

  • Accurate estimations is an oxymoron.
  • From his past look at percentiles: using the 85th percentile, ~90% of the time teams matched or beat it — go there to be conservative.
  • Generally he finds around the 70th percentile works.
  • Look at forecast variation, decide, and watch the future: if at the 70th you did way more, drop to the 60th.
  • The beauty is these techniques are context-specific and embrace the changes teams go through — play with percentiles to find your context.

12.3 Q3 — With “stop and organize,” what happens to ongoing work / people who free up in between (planning events)?

  • Not everyone attends planning — from a team of 10, you’d pick 2–3 people.
  • The ongoing / keep-the-lights-on work and finishing off features continues meanwhile.

12.4 Q4 — How do you represent enterprise architecture work in agile workflows?

  • “Enterprise architecture and agile in the same sentence often don’t really gel.”
  • What has worked: architects work closely with teams so technical decisions align with organizational architecture strategy.
  • Also a big upfront portfolio intake where enterprise architecture checks alignment with technical direction.
  • Effectiveness varied — “in some instances it really didn’t.”

12.5 Q5 — (Client-project scenario) How to forecast for a brand-new client engagement?

  • As a team, estimate a throughput range — how many items per week.
  • Probably pick a 95th percentile to be conservative on risk, caveated by having no experience with the client/org.
  • After a few weeks, reforecast continually (viewable daily) — “covering your back” while learning.

12.6 Q6 — “I’d skip crucial arguments because ROI is bad short-term and I’m avoidant anyway — isn’t that bad?”

  • “I’m not a therapist.”
  • It depends on what it does for you, your org, your relationships.
  • Try working with someone who is your opposite and understand their needs.
  • References the keynote’s desert/forest metaphor (Kent Beck’s keynote): if you’re a “forest person,” spend time with a “desert person” and see if the thinking is that bad.

12.7 Q7 — Conservative waterfall stakeholders starting many features at once and unwilling to prioritize — how to get them on board?

  • Let them experience the consequences via simulations — e.g., getKanban, the “featureban” game from Mike Burrows.
  • Use the Monte Carlo data to show that working on, say, 20 features at once wrecks delivery — they come at it from a delivery perspective, so show the consequence of their actions.

12.8 Q8 — How to forecast when team membership constantly changes due to management decisions?

  • Don’t forecast too far out.
  • If the team is constantly changing, forecast short-term, not for the whole quarter.

12.9 Q9 — Teams that aren’t good at breaking down items — any tips?

  • Use the slide references: Neil Kick’s capability slicing is a great one.
  • Most effective in his experience: Jeff Patton’s story mapping — practice on a fictional context, then apply to your own.
  • Story mapping “visualizes everything so there’s nothing hiding” — everyone sees the different options.

People & References Cited

  • Nick Brown — speaker; principal flow consultant at Thrive Partners; former agility lead at PwC, Nationwide, Royal Mail, ASOS; builds open-source Jira/Azure DevOps tools; once owned a racehorse (broke even).
  • Prateek Singh — probabilistic-thinking inspiration; the “how many bottles of whiskey in four months” talk and his book.
  • Neil Kick — slicing techniques (capability, functional, implementation slicing).
  • Jeff Patton — story mapping; also the alignment/“different understandings” image.
  • Carl Scotland — quoted “that’s not my agile.”
  • Mike Burrows — creator of the featureban simulation game.
  • “Dan” — colleague referenced re: cycle-time averages and a related same-conference talk.
  • Kent Beck — the referenced keynote (desert/forest/genie metaphor).
  • Companies/orgs: PwC, Nationwide, Royal Mail, ASOS, Thrive Partners; the anonymized ~100-team organization.
  • Tools/products: Jira, Azure DevOps, Miro, Smartsheet (Gantt template), Agile Digest (Excel template), Scrum Alliance (case study), getKanban; free GitHub templates for capacity planning and epic/feature flow metrics.
  • Frameworks/methods: Scrum, Kanban, SAFe (normalized story points), LeSS, continuous flow; the book Scaling Simplified.
  • Media reference: Little Britain (“computer says no”); SpongeBob (“how does it work in the real world”).
  • Concepts: evidence-based capacity planning; framework-agnostic scaling; right-sizing; child-item scatter plots and percentile lines; work-item-age chart; thin vertical slices; deterministic vs. probabilistic forecasting; Monte Carlo simulation (~4,000 runs); confidence levels/percentiles as risk levers; feature WIP; continuous reforecasting; color-coded feature forecasts; “stop starting, start finishing”; carryover-aware capacity; teams → platforms → domains rollup; delivery plan vs. road map; cross-team dependency dots; portfolio alignment to strategic pillars with monetary value.

Video: https://www.youtube.com/watch?v=BQDILfWiRAc — Transcript via yt-transcript.sh; outline generated from the transcript.